
A fixed contract price gives you a clear selling price. It also leaves you responsible for managing the costs of delivering the work. A cost-plus contract gives you a way to bill actual costs, but only the costs the agreement allows.
Construction contract types affect what you can bill, which overruns you'll absorb, and what your accounting team needs to track. Lump sum, cost-plus, unit price, and guaranteed maximum price (GMP) contracts each put different demands on your billing and job reports.
Under a lump sum contract, you agree to complete a defined scope for a set price. That price needs to cover the costs included in your scope, overhead, and profit. Changes to the price depend on the adjustment provisions in the contract.
For work within that scope, you generally carry the risk of cost overruns and keep the benefit of savings. Say your contract is $500,000 and your estimated job costs are $425,000. That leaves $75,000 of estimated gross profit. If those costs rise to $460,000 without a price adjustment, gross profit falls to $40,000.
Progress billing is common. Your payment application may use a schedule of values to show completed work, stored materials, prior billings, and retainage. The contract controls what you can bill and when.
Your job reports need a current estimate of the cost to finish. Waiting until the job is complete to find out that labor ran over budget leaves you little room to respond. Track change orders separately so the team can see the added costs, approval status, and any supported adjustment to the contract value.
A cost-plus contract reimburses you for allowable costs and pays an agreed fee. The fee may be a fixed amount or a percentage of a defined cost base. Some cost-plus agreements also include a maximum price.
The owner generally carries more of the cost risk than under a lump sum contract. You still need to control costs and follow the agreement. Unapproved purchases, excluded overhead, unsupported labor charges, or costs outside the agreed scope can leave you with expenses you can't recover.
The accounting team needs to distinguish recorded job costs from billable costs. Keep invoices, time records, subcontractor charges, and other required support tied to the job. Use the agreed rates and fee calculation. Missing documentation can delay a billing even when the work is complete and the costs are already on your books.
A unit price contract sets a rate for a measurable amount of work, such as a cubic yard of concrete or a linear foot of pipe. The amount billed depends on the quantities completed and accepted under the contract.
At $80 per linear foot, 1,000 accepted feet produce an $80,000 billing before retainage or other adjustments. Your profit depends on what it costs to install each foot. Extra crew hours, material waste, or equipment downtime can reduce your margin even when you bill the correct quantity.
The owner generally carries the risk that more units will be needed. You carry the risk that each unit will cost more to produce than you estimated. Check for provisions that adjust rates when quantities change substantially. Your reports should connect field measurements, billed quantities, and cost per unit so disagreements or productivity problems show up early.
A GMP contract commonly reimburses allowable costs plus a fee, with a ceiling on the owner's payment. Approved changes or other adjustments permitted by the agreement can change that ceiling.
You need to monitor the remaining room under the cap. If allowable costs plus your fee reach $2.05 million and the GMP remains $2 million, the $50,000 difference generally reduces your return on the job. A current cost forecast matters well before you reach that point.
The agreement also determines how contingency, allowances and change orders, and savings are handled. Finishing below the GMP doesn't automatically mean you keep the difference. Savings may go to the owner or be shared. Keep the current GMP, approved adjustments, costs incurred, remaining commitments, and estimated cost to finish visible in the job reports.
The contract tells you what you can charge and how to request payment. Your billing method still needs to be reconciled with the revenue you've earned and the cash you've collected. Those amounts can differ under any of these contract types.
Under U.S. GAAP, ASC 606 determines when revenue is recognized. Many construction contracts qualify for recognition over time, but the contract's terms and the applicable criteria need to be assessed. For qualifying work, the measure of progress might use costs incurred relative to estimated total costs or a suitable measure of completed output. A contract label or an invoice alone doesn't determine earned revenue.
Your WIP report should connect the current contract value, job costs, estimates, earned revenue, and billings. Keep collections and retainage visible in the supporting reports. That gives you a way to explain both the job's margin and its effect on cash.
Give accounting and project management the same understanding of the contract. Before the first billing, confirm:
Every contract type needs reliable job costing. A construction controller should make sure the billing process, job reports, and monthly financial statements use consistent information. The reports should make it clear where the job stands and what the team needs to address.
If your accounting team struggles to connect contract terms with billing and job profitability, Levvigo can help. We work with contractors on job costing, WIP preparation, financial reporting, and the accounting processes that support them. Learn more about our outsourced construction accounting.
Book a call with Levvigo to talk through your billing process, job reports, and accounting needs.
A fixed contract price gives you a clear selling price. It also leaves you responsible for managing the costs of delivering the work. A cost-plus contract gives you a way to bill actual costs, but only the costs the agreement allows.
Construction contract types affect what you can bill, which overruns you'll absorb, and what your accounting team needs to track. Lump sum, cost-plus, unit price, and guaranteed maximum price (GMP) contracts each put different demands on your billing and job reports.
Under a lump sum contract, you agree to complete a defined scope for a set price. That price needs to cover the costs included in your scope, overhead, and profit. Changes to the price depend on the adjustment provisions in the contract.
For work within that scope, you generally carry the risk of cost overruns and keep the benefit of savings. Say your contract is $500,000 and your estimated job costs are $425,000. That leaves $75,000 of estimated gross profit. If those costs rise to $460,000 without a price adjustment, gross profit falls to $40,000.
Progress billing is common. Your payment application may use a schedule of values to show completed work, stored materials, prior billings, and retainage. The contract controls what you can bill and when.
Your job reports need a current estimate of the cost to finish. Waiting until the job is complete to find out that labor ran over budget leaves you little room to respond. Track change orders separately so the team can see the added costs, approval status, and any supported adjustment to the contract value.
A cost-plus contract reimburses you for allowable costs and pays an agreed fee. The fee may be a fixed amount or a percentage of a defined cost base. Some cost-plus agreements also include a maximum price.
The owner generally carries more of the cost risk than under a lump sum contract. You still need to control costs and follow the agreement. Unapproved purchases, excluded overhead, unsupported labor charges, or costs outside the agreed scope can leave you with expenses you can't recover.
The accounting team needs to distinguish recorded job costs from billable costs. Keep invoices, time records, subcontractor charges, and other required support tied to the job. Use the agreed rates and fee calculation. Missing documentation can delay a billing even when the work is complete and the costs are already on your books.
A unit price contract sets a rate for a measurable amount of work, such as a cubic yard of concrete or a linear foot of pipe. The amount billed depends on the quantities completed and accepted under the contract.
At $80 per linear foot, 1,000 accepted feet produce an $80,000 billing before retainage or other adjustments. Your profit depends on what it costs to install each foot. Extra crew hours, material waste, or equipment downtime can reduce your margin even when you bill the correct quantity.
The owner generally carries the risk that more units will be needed. You carry the risk that each unit will cost more to produce than you estimated. Check for provisions that adjust rates when quantities change substantially. Your reports should connect field measurements, billed quantities, and cost per unit so disagreements or productivity problems show up early.
A GMP contract commonly reimburses allowable costs plus a fee, with a ceiling on the owner's payment. Approved changes or other adjustments permitted by the agreement can change that ceiling.
You need to monitor the remaining room under the cap. If allowable costs plus your fee reach $2.05 million and the GMP remains $2 million, the $50,000 difference generally reduces your return on the job. A current cost forecast matters well before you reach that point.
The agreement also determines how contingency, allowances and change orders, and savings are handled. Finishing below the GMP doesn't automatically mean you keep the difference. Savings may go to the owner or be shared. Keep the current GMP, approved adjustments, costs incurred, remaining commitments, and estimated cost to finish visible in the job reports.
The contract tells you what you can charge and how to request payment. Your billing method still needs to be reconciled with the revenue you've earned and the cash you've collected. Those amounts can differ under any of these contract types.
Under U.S. GAAP, ASC 606 determines when revenue is recognized. Many construction contracts qualify for recognition over time, but the contract's terms and the applicable criteria need to be assessed. For qualifying work, the measure of progress might use costs incurred relative to estimated total costs or a suitable measure of completed output. A contract label or an invoice alone doesn't determine earned revenue.
Your WIP report should connect the current contract value, job costs, estimates, earned revenue, and billings. Keep collections and retainage visible in the supporting reports. That gives you a way to explain both the job's margin and its effect on cash.
Give accounting and project management the same understanding of the contract. Before the first billing, confirm:
Every contract type needs reliable job costing. A construction controller should make sure the billing process, job reports, and monthly financial statements use consistent information. The reports should make it clear where the job stands and what the team needs to address.
If your accounting team struggles to connect contract terms with billing and job profitability, Levvigo can help. We work with contractors on job costing, WIP preparation, financial reporting, and the accounting processes that support them. Learn more about our outsourced construction accounting.
Book a call with Levvigo to talk through your billing process, job reports, and accounting needs.