Accounting for Change Orders in Construction: Getting the Job Cost, Revenue, and WIP Right

January 17, 2026

If you've been in construction for more than five minutes, you know the original contract is really just a starting point. Owners change their minds. Architects revise drawings. Unforeseen site conditions require additional work. And sometimes the contractor is halfway through the work before anyone has agreed on what it will cost.

Change orders are part of construction. Accounting for them correctly is another matter.

A change order can affect the contract price, estimated costs, revenue recognition, gross profit, billings, and cash flow. When those changes don't make it into the accounting system promptly, the financial statements can tell a very different story from what's actually happening in the field.

The accounting gets particularly interesting when work has been performed but the change order hasn't been approved, or when the owner has authorized the work but hasn't agreed to the price.

Here's how change orders should be handled from an accounting standpoint, including what they do to your work-in-progress (WIP) schedule.

A Change Order Is More Than an Adjustment to the Contract Price

From a project management perspective, a change order documents a change in the scope of work, price, or schedule. From an accounting perspective, it can change the financial performance of the entire job.

A change order is also different from an allowance. I cover that distinction in Change Orders vs. Allowances in Construction.

Suppose a contractor has a $1 million contract with estimated costs of $800,000. The job is expected to generate $200,000 in gross profit, or a 20% gross margin.

Now suppose the owner approves an additional $100,000 of work that the contractor expects will cost $70,000 to complete.

The revised contract price is $1.1 million, estimated costs are $870,000, and projected gross profit increases to $230,000. The projected gross margin increases to approximately 20.9%.

That's straightforward enough. But what happens if the accounting department updates the contract price without updating the estimated costs? Or the project manager revises the cost estimate but doesn't tell accounting about the approved change order?

Neither scenario is particularly unusual, and both can result in misstated revenue and gross profit.

The problem becomes more serious when the contractor is recognizing revenue over time using a cost-to-cost measure of progress, commonly called percentage-of-completion accounting.

How Change Orders Affect Revenue Recognition Under ASC 606

ASC 606, Revenue from Contracts with Customers, establishes the accounting requirements for contract modifications, including construction change orders.

The first question isn't necessarily whether the owner has signed a change order. It's whether the parties have approved a modification that creates or changes enforceable rights and obligations.

Approval can be written, oral, or implied by customary business practices. Whether an agreement is enforceable depends on the contract terms, the facts, and applicable law. A signature is strong documentation, but it's not the only form of approval recognized under ASC 606.

Once a contract modification has been established, the accounting depends on the nature of the additional work.

If the modification adds distinct goods or services and the increase in price reflects their standalone selling prices, it may qualify as a separate contract.

If the remaining goods or services are distinct from those already transferred, but the modification doesn't qualify as a separate contract, the modification is generally accounted for prospectively.

For many construction contracts, however, the work represents a single performance obligation that is satisfied over time. When a change order modifies that same performance obligation, the contractor generally updates the transaction price and its measurement of progress, recognizing the effect through a cumulative catch-up adjustment.

In practical terms, this means an approved change order can affect revenue immediately, even if the contractor hasn't billed for it and hasn't completed all the additional work.

It doesn't mean the contractor automatically recognizes the full amount of the change order as revenue when it's approved.

A Practical Example: How a Change Order Affects WIP

Let's return to our $1 million construction contract.

Before the change order, the contractor had a $1 million contract with estimated costs of $800,000. With $400,000 of costs incurred, the job was 50% complete. The contractor had recognized $500,000 in revenue and $100,000 in gross profit.

After the $100,000 change order, the contract price increased to $1.1 million and estimated costs increased to $870,000. By the end of the reporting period, the contractor had incurred another $60,000 in costs.

With $460,000 in cumulative costs against an $870,000 estimate, the job was now approximately 52.9% complete. Applying the revised percentage to the $1.1 million contract produces approximately $581,609 in cumulative revenue and $121,609 in gross profit.

The change order and additional work increased recognized revenue by $81,609 and gross profit by $21,609.

Notice that the change in recognized revenue is not equal to the $100,000 change order amount, and it isn't determined simply by matching change order revenue against the costs incurred on that particular change order.

The calculation considers the revised contract as a whole.

This example assumes the change order modifies an existing performance obligation that is satisfied over time, the full additional $100,000 qualifies for inclusion in the transaction price, and the contractor uses costs incurred as its measure of progress.

These distinctions matter. The accounting treatment may differ when a change order creates a separate performance obligation or when the additional contract consideration is uncertain.

What About Change Orders That Haven't Been Approved?

This is where construction accounting becomes more complicated.

In the field, there are plenty of situations where additional work needs to proceed before the paperwork catches up.

An owner may direct a contractor to perform additional work but leave the price to be negotiated later. A subcontractor may discover conditions that require additional labor and materials. A general contractor may be waiting for an architect or owner to approve a proposed change.

The contractor is incurring real costs regardless of whether the change order has been approved.

But that doesn't necessarily mean the contractor can recognize the corresponding revenue.

Under ASC 606, the accounting depends on whether the change creates enforceable rights and obligations and, when the amount is uncertain, how much consideration can be included in the transaction price.

Consider an owner who authorizes additional work but hasn't agreed to the price.

If that authorization creates an enforceable contract modification, the contractor may need to estimate the additional consideration under ASC 606's variable consideration guidance.

The amount recognized is subject to an important limitation: the contractor can include variable consideration in the transaction price only to the extent it is probable that a significant reversal of cumulative revenue will not occur when the uncertainty is resolved.

That requires judgment supported by evidence.

The contract terms, correspondence with the owner, historical experience with similar modifications, available pricing information, and the nature of any disagreement all become relevant.

Now consider a different situation. The contractor submits a proposed change order, but the owner disputes responsibility for the additional work. The contractor believes it deserves compensation, but there is no clear agreement or established entitlement.

That proposed change order cannot simply be added to contract revenue because the project manager believes it will eventually be approved.

The contractor must assess whether an enforceable right exists and whether the requirements for recognizing any additional consideration have been met. Claims and disputed modifications can require particularly careful analysis.

Meanwhile, the costs associated with the additional work still need to be recorded and reflected appropriately in the project's cost reporting and forecasts.

For contractors, this can create an uncomfortable result. Additional costs reduce the reported profitability of the job before the contractor has sufficient support to recognize the related revenue.

That's not necessarily an accounting error. It may be an accurate reflection of the uncertainty surrounding the contractor's recovery of those costs.

It also gives management a reason to resolve outstanding change orders rather than allowing them to accumulate.

The Difference Between Contract Revenue and Billing

One of the more common sources of confusion in construction accounting is the assumption that revenue recognition and billing should move together.

They don't necessarily.

A contractor might be entitled to recognize revenue on an approved contract modification before the change order has been incorporated into the billing schedule. Conversely, billing ahead of performance doesn't mean the contractor has earned that revenue.

Returning to our example, suppose the contractor has recognized $581,609 in cumulative revenue after incorporating the approved change order.

If cumulative billings are only $540,000, the job has $41,609 in underbillings.

That difference matters because the contractor has recognized revenue for work performed but hasn't yet billed the customer for all of it.

Depending on the contractual rights involved, the amount may be reflected as a contract asset rather than an unconditional receivable.

Now suppose the accounting department never updates the approved contract value in the WIP schedule. Or the billing department doesn't incorporate the change order into the schedule of values.

The reported underbilling, forecasted profit, and actual cash collections can become disconnected.

A contractor may be earning revenue but failing to bill it. That's an accounting and cash-flow problem, not just a paperwork problem.

And if management isn't reviewing the difference between revenue earned and amounts billed, the problem can continue for months.

Why Change Order Cost Tracking Matters

Revenue recognition is only half the issue. The other half is understanding what the additional work actually costs.

A change order that appears profitable when it's approved may turn out to be a poor decision once all the costs have been captured.

Labor is often the easiest cost to recognize, although even that depends on employees coding their time to the appropriate job and cost code.

Materials and subcontractor costs are usually visible as well, provided invoices are processed promptly and assigned correctly.

The costs that get missed tend to be less obvious.

Additional supervision, equipment, project management time, mobilization, and other costs associated with the change may be absorbed into the original job budget or recorded somewhere else entirely.

Some of those costs may be directly attributable to the change, while others may be covered through the contractor's normal overhead allocation. The distinction matters both for job profitability analysis and for determining which costs are appropriately included in the accounting measure of progress.

The important thing is that the contractor understands the full economic impact of the change.

Where practical, change order costs should be separately identifiable in the job cost system. A separate cost code, phase, or change order identifier makes it easier to compare estimated and actual costs and determine whether the work produced the expected margin.

It also makes it easier to support the amount being requested from the owner if the change remains under negotiation.

Without that detail, a contractor may know that a project lost money but have little idea whether the original estimate was wrong or the change orders caused the loss.

Change Orders Need to Update the Estimated Cost to Complete

This is one of the areas I would pay particular attention to when reviewing a contractor's WIP.

Accounting departments often have reasonably good information about the costs already incurred. The harder part is obtaining reliable estimates of the costs that remain.

Those estimates usually come from project managers, estimators, or operations personnel.

When the scope changes, the estimate needs to change with it.

An approved $100,000 change order with $70,000 of expected costs doesn't just increase the contract price. It also adds work that needs to be performed and costs that need to be incurred.

If the contractor updates the contract price but leaves the estimated total costs unchanged, the percentage-complete calculation will be distorted. Revenue and gross profit may be overstated.

The reverse is also true. If the estimated costs are updated but the contract price isn't, the WIP may understate expected revenue and profitability.

Pending change orders create a related challenge. Even when the contractor cannot yet recognize additional revenue, the estimated costs associated with work that must be performed still need to be evaluated in the forecast.

The WIP should reflect management's best current estimate of the project's financial outcome, applying the appropriate revenue recognition requirements.

It shouldn't simply reproduce the original estimate prepared when the job was awarded.

The Accounting Problem Is Often a Communication Problem

In my experience, change order accounting problems frequently start outside the accounting department.

A project manager knows the owner approved additional work. The superintendent knows the work has already started. The estimator has revised the budget.

But the accounting department doesn't find out until someone notices an unexpected cost variance or an approved change order that hasn't been billed.

Sometimes accounting receives the approved change order but not the revised cost estimate. Sometimes the contract value is updated in one system and not another.

The WIP is only as reliable as the information flowing into it.

For that reason, contractors need a consistent process for communicating change order activity between operations and accounting.

At a minimum, the accounting department should have visibility into approved changes, pending changes, disputed amounts, costs incurred, revised estimates, and billing status.

Those records should agree, or the differences should be understood.

I also think outstanding change orders deserve attention during the monthly WIP review. A change order that has been pending for three months deserves a different level of scrutiny than one submitted yesterday.

The longer a disputed or unapproved change remains unresolved, the more important it becomes to evaluate the estimated recovery, remaining costs, and potential impact on final gross profit.

What Good Change Order Accounting Looks Like

A contractor with good change order controls shouldn't have to wait until a project closes to find out whether its changes were profitable.

The project team should know which changes have been approved, which remain outstanding, what costs have been incurred, and how much additional work remains.

Accounting should know which changes qualify for inclusion in contract revenue, which amounts are still subject to uncertainty, and whether the revised estimates have been incorporated into the WIP.

Billing should know which changes are authorized for invoicing and which are still awaiting approval.

Those functions need to work from consistent information.

The monthly WIP review is a good opportunity to verify that approved contract modifications have been recorded, that pending and disputed amounts have been evaluated appropriately, and that the latest cost estimates reflect the actual scope of work.

It's also an opportunity to identify revenue that has been earned but not billed and to investigate unexpected changes in projected gross margin.

These are basic controls, but they make a substantial difference in the reliability of a contractor's financial reporting.

The Bottom Line

Change orders aren't inherently difficult to account for. What makes them challenging is the combination of changing scope, uncertain pricing, incomplete documentation, and the timing differences between performing work, recognizing revenue, and billing the customer.

The underlying accounting requires more than adding an approved change order to the contract value.

Contractors need to consider the revenue recognition requirements under ASC 606, update their estimated costs, track the actual costs of the additional work, and understand how the changes affect WIP and gross profit.

They also need a reliable process for communicating what's happening in the field to the people responsible for the financial statements.

When those pieces work together, the WIP becomes a useful management tool rather than just another month-end accounting exercise.

And when they don't, contractors can find themselves reporting profits they haven't earned, overlooking losses that are developing, or failing to bill for work they've already performed.

Levvigo provides outsourced construction accounting and financial reporting services for general, specialty, and trade contractors. We help contractors maintain reliable job cost records, prepare and review WIP schedules, and connect project-level financial information with their accounting systems.

If your change orders, job costs, and WIP aren't telling the same story, book a call with Levvigo.

‍

Bryce Wisan, founder of Levvigo

Bryce Wisan, CPA, CCIFP

Founder & Chief

Bryce has spent 15+ years in construction accounting and founded Levvigo to give contractors an outsourced, construction-trained accounting team, business operations support, and practical AI implementation.

Bryce Wisan, CPA, CCIFP

Further reading