In construction accounting, the Work-in-Progress (WIP) report is one of the most critical tools for financial control and project management. It provides a snapshot of where each project stands financially, helping stakeholders understand whether jobs are on track, overbilled, underbilled, or at risk of cost overruns. If you’re new to construction accounting, mastering WIP report preparation is essential for accurate financial reporting and informed decision-making.
A WIP report tracks the financial progress of active construction projects. It compares contract value, costs incurred, billings, and estimated completion to determine:
This report is typically prepared monthly and is a key component of both internal management reporting and external financial statements.
The WIP report serves multiple purposes:
Without an accurate WIP report, companies risk misstating revenue, mismanaging cash flow, and overlooking problem jobs until it’s too late.
A standard WIP schedule includes the following columns:
Start by collecting the following for each active job:
Accurate data is the foundation of a reliable WIP report. Strong internal controls, including purchase orders, support this accuracy.
Add the original contract amount and any approved change orders:
Revised Contract Amount = Original Contract + Approved Change OrdersCombine costs incurred to date with the estimated cost to complete:
Estimated Total Cost = Costs to Date + Estimated Cost to CompleteDivide costs to date by the estimated total cost:
Percent Complete = Costs to Date ÷ Estimated Total CostThis percentage reflects the physical and financial progress of the job.
Multiply the percent complete by the revised contract amount:
Revenue Earned = Percent Complete × Revised Contract AmountThis is the amount of revenue that should be recognized under the percentage-of-completion method.
Subtract billings to date from revenue earned:
Overbilling/Underbilling = Revenue Earned – Billings to DateSubtract the estimated total cost from the revised contract amount:
Estimated Gross Profit = Revised Contract Amount – Estimated Total CostThis figure helps assess whether the job is still on track to meet its original profit goals.
Inaccurate Cost-to-Complete EstimatesIf project managers underestimate remaining costs, the WIP report will overstate profit.
Delayed Change Order ApprovalsFailing to include approved change orders skews contract values and revenue recognition.
Timing Differences in BillingsLarge invoices near month-end can distort over/underbilling calculations if not matched with progress.
Not Updating Forecasts RegularlyWIP reports should reflect the most current information, not outdated estimates.
A well-prepared WIP report is more than a compliance tool—it’s a management dashboard. It helps identify:
By using WIP reports effectively, construction companies can improve cash flow, reduce risk, and make proactive decisions that protect margins.
Preparing a WIP report may seem complex at first, but once you understand the components and calculations, it becomes an indispensable tool for financial control and project success. Accurate WIP reporting ensures that revenue is recognized properly, cash flow is managed effectively, and potential issues are addressed before they escalate.