A contractor can show a profitable job and still need to borrow money to make payroll. Retainage is one reason. You’re paying for labor, materials, and subcontractors while part of your payment stays with the owner.
That makes retainage something you need to manage throughout the job. If your accounting team can tell you the balance but can’t tell you when it should be collected, you don’t have enough information to plan your cash.
Retainage, sometimes called retention, is the portion of a payment withheld until certain contract requirements are met. It gives the owner some protection against incomplete or deficient work. Rates of 5% or 10% are common, although the amount and release requirements depend on the contract and applicable law.
Say you submit a progress billing for $100,000 with 10% retainage. The current payment is $90,000. The remaining $10,000 is held until it becomes eligible for release.
Your job records should show those amounts separately. Otherwise, your receivables report can make $100,000 look available for collection when only $90,000 is currently payable.
There is also a financial reporting detail to get right. Under GAAP, retainage is a receivable when your right to payment is unconditional. If payment still depends on further performance or another condition, the retained amount belongs in the contract asset or liability calculation. FASB’s explanation of retainage presentation covers that distinction.
Whatever the financial statement presentation, you still need to know how much is being held on each job.
Billing, earning revenue, and collecting cash can happen at different times. For contracts where revenue is recognized over time, your WIP report helps reconcile earned revenue with billings. A $100,000 billing doesn’t automatically mean you earned $100,000 that month. And collecting retainage doesn’t create additional revenue if you already recognized it.
The same discipline applies to subcontractor retainage.
Suppose a subcontractor submits a $50,000 invoice for work performed, and you withhold 10%. You have $45,000 currently payable and $5,000 in retainage payable. Under accrual accounting, the full $50,000 belongs in your job costs. Withholding part of the payment doesn’t reduce the cost of the work.
When you eventually pay the $5,000, you’re settling the liability. You shouldn’t record the job cost a second time.
This matters because cash held back from a subcontractor can make your bank balance look better for a while. You still need to account for that obligation in your cash forecast. The retainage you owe and the retainage you expect to collect may come due at different times.
Consider a simple example. You finish a $1 million job with $920,000 in job costs. That leaves $80,000 in gross profit. But if the owner is holding $100,000 in retainage, collecting every regular progress payment leaves you with $900,000 in cash receipts.
If you’ve paid all $920,000 of job costs, you’re funding a $20,000 gap while you wait. The job made money, but it hasn’t produced that money in cash yet.
Across several jobs, those balances can tie up a substantial amount of working capital. They belong in your forecast with realistic collection dates.
Release timing needs attention well before closeout. Some contracts allow retainage to be reduced during the job or released at substantial completion. Others require additional work, documentation, or approvals. AIA’s explanation of the construction payment process describes how partial and full releases can work.
Read those provisions before you sign. A lower rate or an earlier release can reduce the amount of cash you need to carry the job.
As the project approaches completion, accounting and operations need to work from the same information. An unresolved punch list item, missing warranty, or unsettled change order can affect the collection date. Your forecast should reflect what remains to be done.
I would make retainage part of the monthly job review. For each balance, your team should be able to answer:
Review completed jobs as well as active ones. Once the crews move on, it’s easy for a retained balance to sit without anyone taking responsibility for collecting it.
Set up your accounting system to track retainage by job, reconcile it each month, and assign someone to follow through on release requests. Software can keep the balance organized. Your team still has to get the work closed out and the payment collected.
If your retainage balances don’t tie to the books, or your team can’t explain when they should be collected, book a call with me. At Levvigo, we help contractors get their accounting and closeout processes organized so owners have numbers they can use to run the business. Learn more about our outsourced construction accounting.